Claim at v1.1.0

stalled-flood-zone-starts

879aed2187605040e95d8d8ae102eafb80ec33ff94dc68b8494a0bf766188495

Data

{
  "has_outcome": true,
  "kind": "confirmation",
  "lineage": {
    "audit": "docs/lineage_audit.md; data/derived/lineage_audit.json",
    "class": "c",
    "class_meaning": "a shared cache: the query was fetched for an earlier claim and holds this claim's outcome",
    "classes": [
      "c",
      "a"
    ],
    "early_sources": [
      {
        "class": "a",
        "dataset": "ipu4-2q9a",
        "evidence": "Legacy NB permits define the jobs and foundation start dates (the cohort), cached from the construction round. Not the outcome.",
        "fetched": "2026-11-12T15:26:51-05:00",
        "name": "DOB Permit Issuance"
      },
      {
        "class": "a",
        "dataset": "rbx6-tga4",
        "evidence": "DOB NOW foundation permits define the start date and window (exposure), fetched at 11:54:48 for this claim. Not the outcome.",
        "fetched": "2026-11-13T11:54:48-05:00",
        "name": "DOB NOW: Build – Approved Permits"
      },
      {
        "class": "a",
        "dataset": "w9ak-ipjd",
        "evidence": "DOB NOW job filings define New Building jobs (the cohort). Not the outcome.",
        "fetched": "2026-11-12T15:21:36-05:00",
        "name": "DOB NOW: Build – Job Application Filings"
      },
      {
        "class": "c",
        "dataset": "bs8b-p36w",
        "earlier_claim": "stalled-421a-vesting-footings",
        "evidence": "Legacy certificates of occupancy (outcome). Referee: the outcome measure \"was written at 11:56:30, after the registrant had seen the job-level outcomes of stalled-421a-vesting-footings\"; \"The PLUTO flood flags had not been fetched at that time\".",
        "fetched": "2026-11-12T15:20:43-05:00",
        "name": "DOB Certificate Of Occupancy",
        "revealed_deciding_number": "no: the no-CO status of every job and its borough was seen, but not by floodplain, so the deciding difference was not"
      },
      {
        "class": "c",
        "dataset": "pkdm-hqz6",
        "earlier_claim": "stalled-421a-vesting-footings",
        "evidence": "DOB NOW certificates of occupancy (outcome); as for bs8b-p36w.",
        "fetched": "2026-11-12T15:21:05-05:00",
        "name": "DOB NOW: Certificate of Occupancy",
        "revealed_deciding_number": "no: as for bs8b-p36w"
      },
      {
        "class": "a",
        "dataset": "64uk-42ks",
        "evidence": "PLUTO floodplain flags (pfirm15_flag) are the exposure, fetched 11:57:46 for this claim.",
        "fetched": "2026-11-13T11:57:46-05:00",
        "name": "Primary Land Use Tax Lot Output (PLUTO)"
      }
    ]
  },
  "outcome": "stalled-flood-zone-starts",
  "prereg_branch": {
    "name": "prereg/stalled-flood-zone-starts",
    "sha": "fc819e57bae93f53cc3bb1f65682af895a4a4512"
  },
  "prior": 0.35,
  "registered_at": "2026-11-13T11:59:11-0500",
  "registrant": "claude-opus (stalled-construction agent), 13 Nov 2026",
  "registration": {
    "alternatives": [
      "Neighbourhood market: floodplain lots in Queens and Brooklyn are in Rockaway, Coney Island, Red Hook and Gowanus, where demand differs (borough stratification only partly removes it)",
      "Project size: large waterfront projects take longer than 36 months whether or not flood rules slow them",
      "The current PLUTO flag describes the lot today; lot changes after the permit can misplace a job",
      "Selection: the flood rules may deter weak projects before foundation, leaving stronger ones (biases toward no difference)"
    ],
    "graph_evidence": [
      {
        "concepts": [
          "vacant lots"
        ],
        "direction": "n/a",
        "n_findings": null,
        "n_studies": null,
        "pubmed_ids": [
          "23814668",
          "36716893"
        ],
        "summary": "The graph has no finding on flood rules and construction duration. Its vacant-land findings (PMIDs 23814668, 36716893) concern the consequence of land left vacant. The repo's tidal-flooding claims (further-tidal-flooding-*) concern flooding, not building."
      }
    ],
    "id": "stalled-flood-zone-starts",
    "kind": "confirmation",
    "literature": [
      {
        "citation": "NYC Building Code Appendix G (flood-resistant construction), amended 2013 after Hurricane Sandy",
        "doi": null,
        "finding": "Buildings in the 1% floodplain must elevate or flood-proof to the design flood elevation plus freeboard, adding design review and cost."
      },
      {
        "citation": "NYC DCP, Zoning for Coastal Flood Resiliency (2021)",
        "doi": null,
        "finding": "Text amendment allowing height to be measured from the flood elevation; framed as removing a zoning obstacle to building in the floodplain."
      },
      {
        "citation": "FEMA preliminary FIRM 2015 for NYC (used for building code since 2015)",
        "doi": null,
        "finding": "The 2015 preliminary maps enlarged the 1% floodplain; Red Hook lies wholly within it."
      }
    ],
    "plan": "Script analyses/stalled/flood_predictor.py, mode 'run', committed with this registration. 3,410 foundation starts in the windows 15 Dec-14 Jun of 2017-2023 (from vesting_cohorts.py); 3,276 match current PLUTO, 401 of them in the 2015 preliminary floodplain (BK 121, BX 19, MN 30, QN 198, SI 33). Outcome stalled_1096 from vesting_exploratory.py (no CO by job number or BBL within 1,096 days). Bootstrap 2,000 draws, seed 20261113, within borough x flood strata. Power check (rule 8): with a rate near 0.38 the standard error is about 0.026, so a true difference of 0.10 gives z_null about 3.9 (D = 15); the test discriminates for differences above about 0.055.",
    "prediction": {
      "direction": "+",
      "magnitude": "Mantel-Haenszel borough-stratified risk difference, flood minus non-flood, of the 36-month no-CO rate: +0.04 to +0.15.",
      "refute_if": "upper 95% bootstrap bound of the stratified risk difference < 0",
      "support_if": "lower 95% bootstrap bound of the stratified risk difference > 0"
    },
    "prior": 0.35,
    "registered_at": "2026-11-13T11:59:11-0500",
    "registrant": "claude-opus (stalled-construction agent), 13 Nov 2026",
    "sha256": "2904af8de8b282f1b3508d91dcd41b6ea9282ca7792838dc3e718b16b9de0f44",
    "statement": "New-building jobs on lots in the 2015 preliminary 1%-annual-chance floodplain fail to reach a certificate of occupancy within 36 months of their first foundation permit more often than jobs elsewhere in the same borough."
  },
  "registration_commit": {
    "commit": "fc819e57bae93f53cc3bb1f65682af895a4a4512",
    "committed_at": "2026-11-13T11:59:11-05:00"
  },
  "registration_file_sha256": "6faf7932b358bc751e403da266e859140706e368de7bfb400ab7a402932b004a",
  "registration_path": "claims/registered/stalled-flood-zone-starts.json",
  "registration_sha256": "2904af8de8b282f1b3508d91dcd41b6ea9282ca7792838dc3e718b16b9de0f44",
  "registration_text": "{\n \"id\": \"stalled-flood-zone-starts\",\n \"kind\": \"confirmation\",\n \"statement\": \"New-building jobs on lots in the 2015 preliminary 1%-annual-chance floodplain fail to reach a certificate of occupancy within 36 months of their first foundation permit more often than jobs elsewhere in the same borough.\",\n \"graph_evidence\": [\n  {\n   \"concepts\": [\n    \"vacant lots\"\n   ],\n   \"n_findings\": null,\n   \"n_studies\": null,\n   \"direction\": \"n/a\",\n   \"summary\": \"The graph has no finding on flood rules and construction duration. Its vacant-land findings (PMIDs 23814668, 36716893) concern the consequence of land left vacant. The repo's tidal-flooding claims (further-tidal-flooding-*) concern flooding, not building.\",\n   \"pubmed_ids\": [\n    \"23814668\",\n    \"36716893\"\n   ]\n  }\n ],\n \"literature\": [\n  {\n   \"citation\": \"NYC Building Code Appendix G (flood-resistant construction), amended 2013 after Hurricane Sandy\",\n   \"doi\": null,\n   \"finding\": \"Buildings in the 1% floodplain must elevate or flood-proof to the design flood elevation plus freeboard, adding design review and cost.\"\n  },\n  {\n   \"citation\": \"NYC DCP, Zoning for Coastal Flood Resiliency (2021)\",\n   \"doi\": null,\n   \"finding\": \"Text amendment allowing height to be measured from the flood elevation; framed as removing a zoning obstacle to building in the floodplain.\"\n  },\n  {\n   \"citation\": \"FEMA preliminary FIRM 2015 for NYC (used for building code since 2015)\",\n   \"doi\": null,\n   \"finding\": \"The 2015 preliminary maps enlarged the 1% floodplain; Red Hook lies wholly within it.\"\n  }\n ],\n \"prediction\": {\n  \"direction\": \"+\",\n  \"magnitude\": \"Mantel-Haenszel borough-stratified risk difference, flood minus non-flood, of the 36-month no-CO rate: +0.04 to +0.15.\",\n  \"support_if\": \"lower 95% bootstrap bound of the stratified risk difference > 0\",\n  \"refute_if\": \"upper 95% bootstrap bound of the stratified risk difference < 0\"\n },\n \"plan\": \"Script analyses/stalled/flood_predictor.py, mode 'run', committed with this registration. 3,410 foundation starts in the windows 15 Dec-14 Jun of 2017-2023 (from vesting_cohorts.py); 3,276 match current PLUTO, 401 of them in the 2015 preliminary floodplain (BK 121, BX 19, MN 30, QN 198, SI 33). Outcome stalled_1096 from vesting_exploratory.py (no CO by job number or BBL within 1,096 days). Bootstrap 2,000 draws, seed 20261113, within borough x flood strata. Power check (rule 8): with a rate near 0.38 the standard error is about 0.026, so a true difference of 0.10 gives z_null about 3.9 (D = 15); the test discriminates for differences above about 0.055.\",\n \"alternatives\": [\n  \"Neighbourhood market: floodplain lots in Queens and Brooklyn are in Rockaway, Coney Island, Red Hook and Gowanus, where demand differs (borough stratification only partly removes it)\",\n  \"Project size: large waterfront projects take longer than 36 months whether or not flood rules slow them\",\n  \"The current PLUTO flag describes the lot today; lot changes after the permit can misplace a job\",\n  \"Selection: the flood rules may deter weak projects before foundation, leaving stronger ones (biases toward no difference)\"\n ],\n \"prior\": 0.35,\n \"registrant\": \"claude-opus (stalled-construction agent), 13 Nov 2026\",\n \"registered_at\": \"2026-11-13T11:59:11-0500\",\n \"sha256\": \"2904af8de8b282f1b3508d91dcd41b6ea9282ca7792838dc3e718b16b9de0f44\"\n}",
  "statement": "New-building jobs on lots in the 2015 preliminary 1%-annual-chance floodplain fail to reach a certificate of occupancy within 36 months of their first foundation permit more often than jobs elsewhere in the same borough."
}

History in this collection

  1. addedv1.0.0Nov 14, 2026this version